Understanding AIU in Colombian Construction

AIU (Administración, Imprevistos, Utilidad) is the standard overhead and profit structure used in Colombian construction contracts. Understanding it correctly is essential for any contractor working in Colombia.

What Does AIU Stand For?

A - Administración (Administration): 5-15%

  • Office expenses
  • Project management salaries
  • Software and technology
  • Legal and accounting fees
  • Insurance premiums
  • I - Imprevistos (Contingencies): 2-5%

  • Unforeseen conditions
  • Weather delays
  • Material price fluctuations
  • Design changes
  • Risk coverage
  • U - Utilidad (Profit): 5-10%

  • Contractor's profit margin
  • Return on investment
  • Business development costs
  • Activate your account and find overhead (AIU) figures for Colombia inside OneEstimate

    OneEstimate is the #1 budgeting software in Colombia: overhead (AIU) figures, APUs and prices already loaded for Colombia. Start free, no credit card.

    Activate my free account

    Typical AIU Percentages

    Project TypeAIUTotal AIU
    Residential8%3%7%18%
    Commercial10%3%8%21%
    Public Works12%4%5%21%
    Industrial10%5%8%23%

    AIU and Taxes

    IVA (VAT) on AIU

    In Colombia, IVA (19%) is applied ONLY to the Utilidad (U) portion:
  • IVA = U × 19%
  • This is a significant advantage vs. applying IVA to the full contract value
  • Retención en la Fuente (Withholding)

  • Applied to the full contract value
  • Rate: 2% for construction contracts
  • Common Mistakes with AIU

  • Applying IVA to total AIU instead of just Utilidad
  • Using the same percentages for all project types
  • Not justifying each component in public bids
  • Forgetting that AIU is applied to direct costs only
  • OneEstimate Calculates AIU Automatically

    Our software understands Colombian AIU rules and calculates everything correctly — including tax implications.

    Start budgeting in Colombia →

    #1 in Colombia

    Everything you came looking for in Colombia is inside OneEstimate

    Activate your free account and find overhead (AIU) figures for Colombia already loaded, ready to apply to your budget. OneEstimate — the #1 construction software in Colombia.

    Activate my free account ✓ Configurable markup • ✓ No credit card

    OneEstimate — the #1 construction software in Colombia for overhead (AIU) figures