What is a Unit Price Analysis (APU)?
A Unit Price Analysis (APU - Análisis de Precio Unitario) is the detailed breakdown of all costs needed to complete one unit of a specific construction activity. It's the foundation of every construction budget.
The APU Formula
Unit Price = Materials + Labor + Equipment + Indirect Costs
Each component is calculated per unit of measurement (m², m³, kg, ml, etc.)
Example 1: Brick Wall (1 m²)
Materials
| Material | Quantity | Unit Price | Total |
|---|---|---|---|
| Brick | 35 units | $0.15 | $5.25 |
| Mortar | 0.025 m³ | $120.00 | $3.00 |
| Water | 10 liters | $0.01 | $0.10 |
| Subtotal | $8.35 |
Labor
| Worker | Productivity | Daily Wage | Cost/m² |
|---|---|---|---|
| Mason | 7 m²/day | $35.00 | $5.00 |
| Helper | 7 m²/day | $20.00 | $2.86 |
| Subtotal | $7.86 |
Equipment
| Item | Rate | Cost/m² |
|---|---|---|
| Tools | 5% of labor | $0.39 |
| Subtotal | $0.39 |
Direct Cost per m² = $8.35 + $7.86 + $0.39 = $16.60
Add indirect costs (25%): $16.60 × 1.25 = $20.75/m²
Example 2: Concrete Column (1 m³)
A concrete column APU includes formwork, rebar, concrete mix, pouring, and curing. Typical range: $250-400 USD/m³ depending on specifications and location.
Example 3: Electrical Installation (1 point)
An electrical point includes conduit, wire, box, switch/outlet, and labor. Typical range: $35-80 USD/point depending on quality and access.
Automate Your APU Calculations
OneEstimate has 10,700+ pre-calculated APUs ready to use. Just select the activity, adjust quantities, and your budget is ready.
Ready to create budgets faster?
Join hundreds of construction professionals already using OneEstimate to win more projects.