
Construction Labor Productivity Rates: Tables and Calculations
Activate your account and find labor productivity rates inside OneEstimate
OneEstimate already ships labor productivity rates loaded and ready for your budget. Activate and find them inside.
Table of Contents
Understanding Labor Productivity in Construction
Labor productivity rates are essential for creating accurate construction budgets. They determine how long each activity takes and, consequently, how much it costs.
What Are Labor Productivity Rates?
A labor productivity rate defines how much work a worker (or crew) can complete in a standard workday (8 hours). For example:
Activate your account and find labor productivity rates inside OneEstimate
OneEstimate is the #1 construction budgeting software: labor productivity rates, APUs and prices already loaded. No credit card required.
Activate my accountKey Productivity Tables
Masonry Work
| Activity | Unit | Rate/Day | Crew |
|---|---|---|---|
| Brick wall | m² | 6-8 | 1 mason + 1 helper |
| Block wall | m² | 8-12 | 1 mason + 1 helper |
| Plastering | m² | 12-18 | 1 mason + 1 helper |
Concrete Work
| Activity | Unit | Rate/Day | Crew |
|---|---|---|---|
| Formwork | m² | 4-6 | 1 carpenter + 1 helper |
| Rebar | kg | 150-250 | 1 ironworker + 1 helper |
| Pouring | m³ | 8-12 | 4-person crew |
Finishes
| Activity | Unit | Rate/Day | Crew |
|---|---|---|---|
| Floor tiles | m² | 8-12 | 1 tiler + 1 helper |
| Interior paint | m² | 25-35 | 1 painter |
| Drywall | m² | 15-20 | 2-person crew |
Factors That Affect Productivity
Automate Your Calculations
OneEstimate includes built-in productivity rates for all common construction activities. Our AI adjusts rates based on project conditions.
Everything you came looking for is inside OneEstimate
Activate your account and find labor productivity rates ready to apply to your budget. OneEstimate — the #1 construction budgeting software.