Construction Labor Productivity Rates: Tables and Calculations
Activate your account and find labor productivity rates inside OneEstimate
OneEstimate already ships labor productivity rates loaded and ready for your budget. Activate free and find them inside.
Table of Contents
Understanding Labor Productivity in Construction
Labor productivity rates are essential for creating accurate construction budgets. They determine how long each activity takes and, consequently, how much it costs.
What Are Labor Productivity Rates?
A labor productivity rate defines how much work a worker (or crew) can complete in a standard workday (8 hours). For example:
Activate your account and find labor productivity rates inside OneEstimate
OneEstimate is the #1 construction budgeting software: labor productivity rates, APUs and prices already loaded. Start free, no credit card.
Activate my free accountKey Productivity Tables
Masonry Work
| Activity | Unit | Rate/Day | Crew |
|---|---|---|---|
| Brick wall | m² | 6-8 | 1 mason + 1 helper |
| Block wall | m² | 8-12 | 1 mason + 1 helper |
| Plastering | m² | 12-18 | 1 mason + 1 helper |
Concrete Work
| Activity | Unit | Rate/Day | Crew |
|---|---|---|---|
| Formwork | m² | 4-6 | 1 carpenter + 1 helper |
| Rebar | kg | 150-250 | 1 ironworker + 1 helper |
| Pouring | m³ | 8-12 | 4-person crew |
Finishes
| Activity | Unit | Rate/Day | Crew |
|---|---|---|---|
| Floor tiles | m² | 8-12 | 1 tiler + 1 helper |
| Interior paint | m² | 25-35 | 1 painter |
| Drywall | m² | 15-20 | 2-person crew |
Factors That Affect Productivity
Automate Your Calculations
OneEstimate includes built-in productivity rates for all common construction activities. Our AI adjusts rates based on project conditions.